01/11/2026
Episode 57 breaks down the daily plan that moved 3,200 tons of mill and overlay through a subdivision of roughly 500 homes in about 60 crew hours. The mill started at 7 each morning and ran a few hundred tons ahead before any trucks were switched over to asphalt, and that same morning gap is when the crew reinstalled 17 speed bumps. When the asphalt orders ran over on Tuesday and Wednesday, two or three extra loads came from a different plant's night shift, which was the only hiccup of the week. Trees overhanging the streets meant the truck beds had to come up and down around them while the paver kept moving. The episode also covers how the HOA and property manager handled the towing and resident calls so the crew never had to stop paving.
Watch the full episode: https://youtu.be/IJ1JkFtbj_c
For more on our company, visit https://www.paveitforwardllc.com