20/10/2026
ποΈ PROJECT PROGRESS UPDATE
2 bedroomed house, Mahalapye flowertown phase 2
Weβre making steady progress on site!
β
*Stage 1: Box Building - DONE*
> Foundation box built, compacted and leveled to perfection.
> β
*Stage 2: Slab Concrete - DONE*
> Solid slab cast, well cured and ready for the next phase.
> β
*Stage 3: Walling to Window Level - DONE*
> Blockwork raised neatly to window level on all sides.
> π *Stage 4: Ringbeam - IN PROGRESS*
> Shuttering and steel fixing in progress. Concrete casting loading...
> Quality work, on schedule. Next up: Walling to roof level!