📐 Calculation of Quantities – RCC Footing Quantity Take-Off
Accurate quantity estimation is one of the most important steps in any construction project. This RCC footing quantity take-off example demonstrates how to calculate concrete volume, dry volume, and the required quantities of cement, sand, and coarse aggregate for multiple footings.
Key Details:
✅ Footing Size: 1.30 m × 1.30 m × 0.30 m
✅ Volume of One Footing: 0.507 m³
✅ Total Wet Concrete (10 Footings): 5.07 m³
✅ Dry Volume (Factor 1.54): 7.81 m³
✅ Concrete Mix Ratio: 1 : 1.5 : 3 (Cement : Sand : Aggregate)
✅ Cement Required: 41 Bags (≈2050 kg)
✅ Sand Required: 2.13 m³ (≈3408 kg)
✅ Coarse Aggregate Required: 4.26 m³ (≈6816 kg)
Important Notes:
Always verify footing dimensions as per structural drawings.
Dry volume factor of 1.54 is commonly used for nominal concrete mixes.
Add 2–3% extra for wastage during material planning.
Actual quantities may vary depending on site conditions and project specifications.