Was able to get osb on all three gable end and wrap the entire house. Installed new metal to cover some old flashing as ...
10/16/2026

Was able to get osb on all three gable end and wrap the entire house.

Installed new metal to cover some old flashing as well.

Next week outside corners, trim pieces and new siding.

Was a shorter day than normal since we are both working tonight’s football game.

Started a new project in the Fowler area, today. We removed most of the siding and wrapped the gable ends.More to come n...
10/08/2026

Started a new project in the Fowler area, today.

We removed most of the siding and wrapped the gable ends.

More to come next week…

Started flooring yesterday (installed 400 sq ft) and continued today (1200 sq ft). It looks great. We pushed hard so we ...
09/24/2026

Started flooring yesterday (installed 400 sq ft) and continued today (1200 sq ft).

It looks great.

We pushed hard so we can finish next week hopefully, flooring, mop board trim and touch painting here and there.

It’s into our 3rd week into the Lafayette commercial project.We removed 1400 sq feet of glue down carpet. Patch several ...
09/04/2026

It’s into our 3rd week into the Lafayette commercial project.

We removed 1400 sq feet of glue down carpet.

Patch several several drywall holes.

Got the computer cables and power feeds cleaned up and hidden to give a better office look.

Got the two smaller rooms painted the new gray color plus hallway.

1 conference room has its Ceiling painted its first coat.

2 conference room started trimming around things.

Hopefully get more painting done this weekend.

Updates on more completed….

Bathroom project is complete and now onto a commercial project in Lafayette. Going to touch up walls in 2 conference roo...
08/20/2026

Bathroom project is complete and now onto a commercial project in Lafayette.

Going to touch up walls in 2 conference rooms, 2 offices. New ceiling and wall paint plus 1600 sq ft of flooring.

Pic to come later

It has been forever since we updated our facebook/project ref bathroom project in Kentland. New vanity, sink top, new to...
08/09/2026

It has been forever since we updated our facebook/project ref bathroom project in Kentland.

New vanity, sink top, new toilet, new solid surface shower walls plus fixtures

Added electrical outlets above sink, insulated walls for warmth and sound proofing.
New flooring and a new door, trim and paint

Had a slight delay with the passing of our drywaller/painter Tom Anderson,unexpectedly!! He will be missed, he was a good guy.

Homeowner was extremely understanding and we found another finisher to compete that part of the project.

Finished this morning!!

Moving to south of Fowler for another bathroom remodel.

Three and a half days into our Kentland bathroom project. Tore out old plaster walls, ceiling and cast iron tub.Removed ...
07/19/2026

Three and a half days into our Kentland bathroom project.

Tore out old plaster walls, ceiling and cast iron tub.

Removed 4 layers of old flooring over flooring.

Insulated walls, updated electrical w two more plug ins.

Framed for a new recessed medicine cabinet.

New 5 ft walk in shower ( base installed)

More to come next week.

Was able to finish the deck project with brand black railing!!!!This afternoon we picked up supplies for a new bathroom ...
07/10/2026

Was able to finish the deck project with brand black railing!!!!

This afternoon we picked up supplies for a new bathroom project we are starting in Kentland next week, plus meet w two customers one for an office remodel in Lafayette and a complete kitchen remodel in otterbein area.

Slipped in a last minute mulch job this morning before the holiday weekend.  The home needed fresh mulch for a family/Ho...
07/03/2026

Slipped in a last minute mulch job this morning before the holiday weekend. The home needed fresh mulch for a family/Holiday weekend.

Like everyone knows it was stupid hot today, but we got a good start rebuilding the deck. Installed vinyl lattice for lo...
07/03/2026

Like everyone knows it was stupid hot today, but we got a good start rebuilding the deck.

Installed vinyl lattice for looks and to keep critters from getting under the deck. Re-enforced a section for a grill to sit on. Installed bracing for the new maintenance free deck boards.

Got almost 2/3rds of it done.

Address

908 E 5th Street
Fowler, IN
47944

Telephone

+17654260527

Website

Alerts

Be the first to know and let us send you an email when Blue Line Construction Llc posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Blue Line Construction Llc:

Shortcuts

Share