FIRE RESTORATION Job Westlake, Huge Full house remodel
1st floor
- total gut
- new Insulation, draft barrier, and fire protection
- new drywall and paint
- new hardwood flooring in kitchen, refurbished flooring in rest of house
- new bathroom tiled shower
-new interior doors, window casing and sills, baseboards, and shoe mold
- new kitchen cabinets
- brand new electrical system
2nd floor
- new insulation, draft barrier and fire protection
- bathroom vanity and shower valve
- brand new electrical system
- basement
New drywall ceiling and lighting
Lengauer Contracting LLC Provided services on this project
Drywall Hanging, all trim work, cabinet install, HVAC, plumbing, insulation, fire protection, dumpster provided, site supervision
Tile work- Roger G
Drywall Taping first and Second floor- Dan W.
Painting - CS Fine Finishes
Electrical- Kingsboro Electric
Hardwood flooring Sanding and Finishing- Hamlin Floors
Drywall Taping Basement- Quest Drywall
Kitchen Cabniet supplier with tops- Lakeview Kitchen and Bath
Special thanks to our suppliers Carter lumber, Wolff brothers supply and Leonard interior supply